After Years of Delays & Well Over Budget, The Central Subway Opens
Just two and a half weeks away, the grand opening of a long-awaited project. The Central Subway will finally (tho not completely) be opened. An extension of the T Third Line route on 3rd Street, the Central Subway will extend through SOMA, the FiDi and Chinatown. Last week, the city

After 19 years, Van Ness Construction Project Nears Completion!
Van Ness street, the construction project that lasted a generation, is “near completion” according to MUNI this week, and by ‘near completion’, they mean ‘buses can use it probably some time in 2022’. Ah, San Francisco…in less than a year you oversaw the planning and construction of over 300 parklets,

New SF Subway Line Taking Longer to Build Than Golden Gate Bridge in 1930’s
The new SF Subway Line connecting the SOMA with Chinatown, is taking twice as long to build as it took to build the entire Golden Gate Bridge in the 1930’s.